Lateral 43 Pipeline Project Update 01/03/2025

Lateral 43 Pipe Line Project

Project Update

January 3, 2025 Update

Wet weather has impacted the progress of work on the pipeline, making working conditions in the field wet and slick, but overall progress is being made.

For this first week in January crews have completed the following:

·         Built the widening for Highway 97 crossing.

·         Welded 63” pipe and tees

·         Installed 8” and 16” on the 43-2

·         Continued building ARV’s and Turnouts.

 

The week of January 5th -11th the following work is planned:

·         Continued welding work on 63”

·         Finish backfill of 43-2

·         Pave highway widening and begin box culvert demolition

·         Continue installing turnouts and ARV’s on the 43-2

·         Begin welding on the 43-3

 

Information provided by Ben Vavallaro, Project Manager Taylor Northwest

 

 

 

 

 

 

 

 

 

 