Lateral 43 Pipeline Project 2025 Updates

Keyboard, notepad, pen, small plant on desk with text "Latest Update".

Executive Summary Report Lateral 43 Project Week of 01/10/2025

NUID Executive Summary Report 1.10.2025.pdf

Current Drone Pictures from Lateral 43 PL Project

https://nam11.safelinks.protection.outlook.com/?url=https%3A%2F%2Fdrive.google.com%2Ffile%2Fd%2F1doSN-YylndcegsoaNg_TFVS_lZjCteXV%2Fview%3Fusp%3Ddrive_web&data=05%7C02%7C%7C9c12a001eb584a603abf08dd1a16e6d0%7C21da1051393f4ddc88aad49aa2c8b9f4%7C0%7C0%7C638695407871798718%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=ggKzP9bwHt1DUJk7Rix5vUKBQJ7jlvIag6C%2FPHYhciY%3D&reserved=0

January 29, 2025 drone footage of pipeline project.

https://nam11.safelinks.protection.outlook.com/?url=https%3A%2F%2Fdrive.google.com%2Ffile%2Fd%2F1NisRw32kh3x5EF8DyK-I06CgVlHjuHsw%2Fview%3Fusp%3Ddrive_web&data=05%7C02%7C%7C8a08f827323f4a981ddd08dd409507da%7C21da1051393f4ddc88aad49aa2c8b9f4%7C0%7C0%7C638737731031646932%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=5uXGedqo0NnP456eD0mQHJftcma8Ch5NME9vebWRmVc%3D&reserved=0

43 Later Project Update 02.14.2025.pdf

Executive Summary for week of 2/14/25 from Ben Cavallaro, Project Manager Taylor Northwest

  • Began excavating west of 97 on the 43 lateral
  • Continued welding 63" 
  • continued backfill of the 43 lateral
  • Received the remainder of 63" from the supplier
  • Installed the PRV on the 43-2

Next week crews will:

  • Continue welding and installing 63"
  • continue on clean up of the 43-2
  • pull 63" through the highway crossing
  • Begin welding west of 97
  • Complete energy dissipaters on 43-2, and 43-5
  • Begin to fill and pressure test: 43-2, 43-3, 43-5